The installation took place at a substation in Abqaiq, Saudi Arabia. Under supervision of Aramco Engineers, the Team installed a CL3AM Unit, including Monitoring System on the Transformer under live conditions. After the successful installation the unit was started, the removal of moisture from the Transformer oil began and could be followed on the monitoring unit. The trial period for this project will be 6 months in order to prove a sustainable removal of moisture from the Transformer Insulation Paper.

    Medium img 0698

    Installation of the unit

    Medium img 0707

    Installation on stainless steel pipework

    Medium img 0746

    Finished installation

    Medium img 1025

    First results